Work given to a company

Grinding off the old road surface and laying new asphalt on Magnolia Bend

The government's number for this: R09G061

What is happening?

Grinding off the old road surface and laying new asphalt on Magnolia Bend. The parish describes the spot as: From Chamalet to Dead End. Length of the job: 664 Feet. The parish set aside $69,000 for this job and signed a contract for $78,108.04. That is $9,108.04 more than it set aside.

Where is it happening?

Magnolia Bend. From Chamalet to Dead End.

Why does it matter to me?

The Rabbit Hole has not written an explanation for this kind of record yet.

What could change?

It was approved. Any building or digging still needs permits before work can start.

When will a decision or vote happen?

No date has been published yet.

What was the final decision?

Work given to a company.

Can I speak about it?

The record does not say where this gets heard, so we cannot tell you where to speak about it.

The government's exact words

We put the plain English first. This is the wording the government itself published, copied exactly, in case you need it.

Magnolia Bend — Mill & Overlay
STREET: Magnolia Bend RIN: R09G061 ACTION: Road ITEM: Mill & Overlay LENGTH: 664 Feet LOCATION_DETAILS: From Chamalet to Dead End BUDGET_PRICE: 69000 CONTRACT_PRICE: 78108.04

How The Rabbit Hole got this

Retrieved
6 September 2026, 5:05pm
Method
Read directly from the government’s own mapping server
Note
St. Tammany Parish 2023 Budgeted Road Projects layer. Carries the budgeted price and the contracted price for each job.