The government's number for this: R10C004
Grinding off the old road surface and laying new asphalt on Lowe Davis Rd. The parish describes the spot as: From Asphalt change @ Allen Rd. Going West to Asphalt Change at station 66+67. Length of the job: 6,667 Feet. The parish set aside $353,000 for this job and signed a contract for $346,065.02. That is $6,934.98 less than it set aside.
Lowe Davis Rd. From Asphalt change @ Allen Rd. Going West to Asphalt Change at station 66+67.
The Rabbit Hole has not written an explanation for this kind of record yet.
It was approved. Any building or digging still needs permits before work can start.
No date has been published yet.
Work given to a company.
The record does not say where this gets heard, so we cannot tell you where to speak about it.
We put the plain English first. This is the wording the government itself published, copied exactly, in case you need it.
Lowe Davis Rd. — Mill & Overlay
STREET: Lowe Davis Rd. RIN: R10C004 ACTION: Road ITEM: Mill & Overlay LENGTH: 6,667 Feet LOCATION_DETAILS: From Asphalt change @ Allen Rd. Going West to Asphalt Change at station 66+67 BUDGET_PRICE: 353000 CONTRACT_PRICE: 346065.02